Docks & Harbors Projects
2023 - Aurora Harbor Rebuild - Phase III
Project Details
CBJ Contract #: DH23-015Contractor: Trucano Construction Co.
Consultant: D&H Engineering (In House)
Construction Cost: $4,269,650
Start Date: TBD
Completion Date: June, 2024
Contact: Matthew D. Sill, P.E. CBJ Port Engineer
Phone: (907) 586-0398Email: [email protected]
Project Overview
This project is the third phase in the Aurora Harbor Rebuild project.
The scope of work includes the construction and installation of new headwalk, one new mainwalk and the associated finger floats as well as a complete potable water system, fire suppression system and electrical system. Additional work includes refurbishing the existing gangway and gangway landing float and re-installing each of them.
Associated Documents