Engineering Projects

ALL Projects
CURRENT PROJECTS

Kaxdigoowu Heen Dei Trail Relocation

BE19-17

Completion Date: 
June 15, 2020

Contractor: Southeast Earthmovers, Inc.

Contract Amount: $239,581


Project Manager: Keri Williamson
Phone: 907-586-5200
Email: [email protected]
No Featured Image - Stock photo with plans and pencils and the words No Featured Image.

Description:

Work includes the installation of a new trail alignment and reclamation of existing Kaxdigoowu Heen Dei along the Mendenhall River. Work generally includes clearing and grubbing, excavation, usable excavation, shot rock borrow, base course grading D-1, storm drain culverts, construction surveying, hydroseeding, filter fabric, asphalt pavement, and other miscellaneous related work.