Engineering Projects
CBJ Headworks Improvements
BE17-033
Completion Date: January 17, 2011
Contractor: Carver Construction, LLC
Contract Amount: 2,422,930
Description:
Installation of new perforated plate screens and screening washer/compactor, replacement of influent piping, construction of new concrete channels and other miscellaneous work at the MWWTP and the JDTP.