Mendenhall Blvd Paving - Poplar Ave to Loop Rd
BE19-252
Completion Date: September 13, 2019
Contractor: SECON
Contract Amount: $329,314
Description:
The work for Mendenhall Blvd Paving – Poplar Avenue to Loop Road generally consists of surveying existing road grades. The removal of existing pavement, excavation of roadway and placement of 2-inch shot rock /D-1 base course as shown on drawings. Installation of approximately 228 LF of 6”CPP underdrain. Removal and replacement of water valve boxes, manhole frames and covers and reset centerline control monuments. Pave with 2-1/2 inches or 3 inches of Type IIA, Class B AC Pavement as shown on the drawings.