JNU Taxiway A Rehabilitation, Taxiway D-1 Relocation, and Taxiway E Realignment

Project Number: BE19-218Project Manager: Mike Greene
Completion Date: 2021-10-29Project Manager Phone: 907-586-0453
Contract Amount: $21,801,430Project Manager Email: [email protected]
Contractor: SECON
Description:

Phase 1: This work phase is to be used by the Contractor to complete the administrative and
materials submittal process, to order materials, to mobilize to the site and to begin work on the
construction of the Airfield Lighting Regulator Vault (ALRV).

Phase 2: Work to be completed in this phase will include the relocation of Taxiway D1, the
rehabilitation and extension of Taxilane H and the completion of the ALRV.

Phase 3: Work to be completed in this phase will include the realignment of Taxiway E and the
rehabilitation of Taxiway A.