Project Number: BE18-053 | Project Manager: Mike Greene |
Completion Date: 2019-05-31 | Project Manager Phone: 586-0453 |
Contract Amount: $473,720 | Project Manager Email: [email protected] |
Contractor: Southeast Earthmovers Inc. |
Description:
The Work generally consists of major improvements to the float pond outlet pipe and valve control structure.
|