Project Number: BE17-033 | Project Manager: Lori Sowa |
Completion Date: 2011-01-17 | Project Manager Phone: 907-586-0875 |
Contract Amount: 2,422,930 | Project Manager Email: [email protected] |
Contractor: Carver Construction, LLC |
Description:
Installation of new perforated plate screens and screening washer/compactor, replacement of influent piping, construction of new concrete channels and other miscellaneous work at the MWWTP and the JDTP.
|