Recycling Baler and Wire Tier Installation

Bid Due Date: blank 2/6/2015

Pre-Bid Meeting:

Type of Solicitation: Bid
Bid/RFP Number: E15-147
Date Advertised: 
Construction Estimate: $640,000
Plan Holders List: Current List
Cost of Bid Documents: $35
Project Description:

This project consists of, but is not limited to, installation of a new industrial recycling baler with wire tier and related accessories per the design drawings and specifications.

Result

Low Bidder: Silver Bow Construction

Bid Opening/Proposal Date: 2/6/2015
Bid Amount: $506,300
Bid/RFP Result Summary: View Document
Award Date: 3/9/2015
Award Amount: $506,300
Notice of Award:  View Document