CDD Logo

Casey Shattuck Reconstruction, Phase V

Bid Due Date: blank 3/11/2010

Pre-Bid Meeting:

Type of Solicitation: Bid
Bid/RFP Number: E10-187
Date Advertised: 
Construction Estimate: $1,583,000.00 - Approx
Plan Holders List: Current List
Cost of Bid Documents: $45.00
Project Description:

This Project consists of installation of an underground storm drainage system, replacement of water system and some segments of the sanitary sewer systems, replacement of the roadway embankment to a 24-inch depth, new asphalt pavement, concrete sidewalks and curb and gutter, removal and replacement of fences, relocation of landscaping items, removal of trees and shrubs, and miscellaneous related work.

Result

Low Bidder: Arete Contruction Corp.

Bid Opening/Proposal Date: 3/11/2010
Bid Amount: $1,221,904.00
Bid/RFP Result Summary: View Document
Award Date: 0000-00-00
Award Amount: 
Notice of Award: 
Bid/RFP Documents:
Addenda and Additional Information:
  • Addendum No. 1 - E10-187