Treadwell Mine Office Building Rehabilitation - Phase III

Bid Due Date: white pixel, space holder 6/28/2018

Pre-Bid Meeting:

Type of Solicitation: 
Bid
Bid/RFP Number: 
E19-025
Date Advertised: 6/1/2018
Construction Estimate: $50,000
Plan Holders List: Current List
Cost of Bid Documents: $25

Description:

This Project consists of cleaning of the interior and exterior concrete walls and paint the exterior walls and trim of the Treadwell Mine Office Building, and miscellaneous items of work.

Result

Low Bidder: Silver Bow Construction

Bid Opening/Proposal Date: 6/28/2018
Bid Amount: $55,800
Bid/RFP Result Summary: View Document
Award Date: 7/31/2018
Award Amount: $55,800
Notice of Award:  View Document
Addenda and Additional Information:
  • Addendum No. 1
  • Addendum No. 2