Juneau International Airport (JNU) Main Entry Renovation
Bid Due Date:
9/14/2011
Pre-Bid Meeting:
Type of Solicitation: Bid
Bid/RFP Number: E12-036
Date Advertised:
Construction Estimate: $1,000,000
Plan Holders List: Current List
Cost of Bid Documents: $100
This project consists of replacement of main entry of terminal. Work includes new steel frame, glass canopy and curtain wall, miscellaneous mechanical, electrical, and interior finishes.
Result
Low Bidder: McGraw Custom Construction
Bid Opening/Proposal Date: 9/14/2011
Bid Amount: 1,014,000
Bid/RFP Result Summary: View Document
Award Date: 0000-00-00
Award Amount:
Notice of Award:
Addenda and Additional Information:
Addendum 1
Conformed After Bid - A201, A601 D201
Conformed After Bid - Electrical Drawings