Melvin Park Playground Improvements
Bid Due Date:
10/6/2011
Pre-Bid Meeting:
Type of Solicitation: Bid
Bid/RFP Number: E11-228
Date Advertised:
Construction Estimate: $224,000.00
Plan Holders List: Current List
Cost of Bid Documents: $30.00
The WORK covered in the Contract Documents generally includes: demolition of existing structures, excavation, drainage, pouring of concrete slabs, laying of concrete pavers, construction of concrete block walls and timber walls, landscape planting, installation of playground equipment and surfacing, installation of wood fence, bollards, picnic tables, and asphalt concrete pavement. Work also includes painting of the bathroom building and privacy walls and all other Work as described in these Contract Documents.
Result
Low Bidder: North Pacific Erectors
Bid Opening/Proposal Date: 10/6/2011
Bid Amount: $197,500.51
Bid/RFP Result Summary: View Document
Award Date: 0000-00-00
Award Amount:
Notice of Award: