CDD Logo

Central Avenue Sidewalk

Bid Due Date: white pixel, space holder 6/8/2011

Pre-Bid Meeting:

Type of Solicitation: 
Bid
Bid/RFP Number: 
E11-270
Date Advertised: 5/18/2011
Construction Estimate: $310,000
Plan Holders List: Current List
Cost of Bid Documents: $30.00

Description:

This Project consists of removal of existing chip seal surfacing, excavation of existing base course, grading for a sidewalk and reditching on the northeast side of the roadway. Installation of 2-inch minus shot rock base, curb and gutter, storm drainage culverts, curb inlets, AC pavement on roadway and sidewalk and fog seal coat and all related work as described in the contract documents.

Result

Low Bidder: Arete Construction Corp.

Bid Opening/Proposal Date: 6/8/2011
Bid Amount: $249,634
Bid/RFP Result Summary: View Document
Award Date: 0000-00-00
Award Amount: 
Notice of Award: