CDD Logo

Mendenhall Wastewater Treatment Plant Biosolids Dryer Facility

Proposal Due Date: white pixel, space holder 7/11/2017

Pre-Bid Meeting:

Type of Solicitation: 
Bid
Bid/RFP Number: 
E17-133
Date Advertised: 5/25/2017
Construction Estimate: $14,800,000
Plan Holders List: Current List
Cost of Bid Documents: $125

Description:

Demolition of the existing ABF building and construction of a new ~18,734 GSF metal clad CMU building atop the existing foundations.