Riverbend Elementary School Water Damage Repair

Bid Due Date: 2022-03-24 white pixel, space holder

Pre-Bid Meeting: 2022-03-11

Type of Solicitation: Bid
Bid/RFP Number: BE22-252
Date Advertised: 2022-03-04
Construction Estimate: Between $850,000 and $900,000
Plan Holders List: Current List
Cost of Bid Documents: -----
Project Description:

Base Bid Item No. 1. Remove temporary flooring.  Prep surfaces and install new finishes including flooring, wall coverings and paint as indicated in the drawings providing permanent repairs from flood damage. This may include minimal Mechanical and Electrical work to removed and reinstall existing equipment as needed.

Base Bid Item No. 2. Provide water mitigation to the concrete slab as indicated in Specification Section 033511 Concrete Floor Finish and Contract drawings.  (Removal of temporary floor and cabinets shall be included in Bid Item 1.)

Additive Alternate No. 1. Paint exposed GWB ceiling structure in Library 113.

 

Result

Low Bidder: Carver Construction, LLC

Bid Opening/Proposal Date: 2022-03-24
Bid Amount: $1,032,768.00
Bid/RFP Result Summary: View Document
Award Date: 2022-04-22
Award Amount: $1,032,768.00
Notice of Award:  View Document