Robbie Road, Ling Court & Laurie Lane Reconstruction
Bid Due Date:
2022-02-09
Pre-Bid Meeting: 2022-01-26
Type of Solicitation: Bid
Bid/RFP Number: BE22-050
Date Advertised: 2022-01-18
Construction Estimate: Between $800,000-900.000
Plan Holders List: Current List
Cost of Bid Documents: -----
The WORK includes reconstruction of Robbie Road, Ling Court, and Laurie Lane. Work generally includes clearing and grubbing, excavation, 2” minus shot rock with D-1 base course, storm drain improvements, replacement of existing water main, new water services, new fire hydrants, new sanitary sewer manholes, a new sewer service, asphalt pavement, mailboxes, traffic control signs, and other miscellaneous related WORK.
Result
Low Bidder: Coogan Construction Company
Bid Opening/Proposal Date: 2022-02-09
Bid Amount: $898,346.00
Bid/RFP Result Summary: View Document
Bid/RFP Documents:
Addenda and Additional Information: