CDD Logo

Calhoun Avenue Reconstruction, Phase 1

Bid Due Date: 2021-12-14 white pixel, space holder

Pre-Bid Meeting: 2021-11-30

Type of Solicitation: Bid
Bid/RFP Number: BE21-117
Date Advertised: 2021-11-18
Construction Estimate: $1,250,000 - $1,750,000
Plan Holders List: Current List
Cost of Bid Documents: -----
Project Description:

The WORK covered in the Contract Documents includes reconstruction of Calhoun Avenue from the Gold Creek Bridge to the intersection of West 7th Street. WORK generally includes concrete slab removal, excavation, shot rock borrow, 2” minus shot rock with D-1 base course, asphalt pavement, curb and gutter, concrete sidewalk, ADA ramps, replacement of storm drain pipe, catch basins, manholes, sewer pipes, insulated HDPE water main and apparatuses, traffic control markings, signs and other miscellaneous WORK

Result

Low Bidder: North40 Construction Corp.

Bid Opening/Proposal Date: 2021-12-14
Bid Amount: $1,885,217.00
Bid/RFP Result Summary: View Document
Award Date: 2022-01-24
Award Amount: $1,885,217.00
Notice of Award:  View Document
Bid/RFP Documents:
Addenda and Additional Information: