CDD Logo

Pioneer Avenue Reconstruction, Phase III

Proposal Due Date: white pixel, space holder 11/8/2013

Pre-Bid Meeting Date: 

Type of Solicitation: Bid
Bid/RFP Number: E14-022


Description:

This Project consists of reconstruction of Pioneer Avenue from No. 3151 Pioneer Avenue through the Blueberry Hills Road intersection, the installation of an 8-inch, 10-inch and 16-inch HDPE pipe along Pioneer Avenue and into the Blueberry Hills Road intersection, a temporary 6-inch HDPE water pipe by-pass system, new underground storm drainage and replacement of the street and the right side sidewalk embankments to a 24-inch depth, new asphalt pavement, concrete sidewalks, and curb and gutter

Result

Low Bidder: Arete Construction, Corp.

Bid Opening/Proposal Date: 11/8/2013
Bid Amount: $1,034,925.00
Bid/RFP Result Summary: View Document
Award Date 12/23/2013
Award Amount: $1,034,925.00
Notice of Award: View Document