CDD Logo

Twin Lakes Lift Station Replacement Project

Proposal Due Date: white pixel, space holder 8/26/2011

Pre-Bid Meeting Date: 

Type of Solicitation: Bid
Bid/RFP Number: E12-059


Description:

DESCRIPTION OF WORK. This Project consists of installing approximately 20 linear feet of 8-inch diameter gravity sewer, 40 linear feet of 10-inch diameter gravity sewer; 40 linear feet of 6-inch sewer force main; installing a new sewer manhole: removing and replacing asphalt paving; demolition of an existing sewage lift station; installation of a new sewage pump station with submersible pumps along with associated electrical work and controls; a trailer mounted portable generator; a trailer mounted portable pump and other miscellaneous items of WORK.

COMPLETION OF WORK. The WORK must be completed by July 1, 2012.

Result

Low Bidder: Miller Construction Company, Ltd.

Bid Opening/Proposal Date: 8/26/2011
Bid Amount: $586,050
Bid/RFP Result Summary: View Document
Award Date 0000-00-00
Award Amount: 
Notice of Award: View Document