Bartlett Regional Hospital Roof Replacement

Bid Due Date: white pixel, space holder 6/8/2011

Pre-Bid Meeting:

Type of Solicitation: 
Bid
Bid/RFP Number: 
E11-286
Date Advertised: 5/18/2011
Construction Estimate: $1,700,000
Plan Holders List: Current List
Cost of Bid Documents: $50

Description:

The Project includes removal of the existing IRMA roof system down to the structural roof deck; installation of a sloping, insulated fully adhered single ply roof membrane roofing system to drains, and mechanical and electrical modifications as needed to accommodate new roof.

Result

Low Bidder: Universal Roofing of Alaska

Bid Opening/Proposal Date: 6/8/2011
Bid Amount: $1,870,000
Bid/RFP Result Summary: View Document
Award Date: 0000-00-00
Award Amount: 
Notice of Award: