Gruening Park Lift Station Stand-Alone Lift Station

BE21-264

Completion Date: 
May 01, 2022

Contractor: ENCO Alaska Inc.

Contract Amount: $1,170,275


Project Manager: Paul Beck
Phone: 907-586-0800 Ext. 4191
Email: [email protected]
No Featured Image - Stock photo with plans and pencils and the words No Featured Image.

Description:

The WORK covered in the Contract Documents includes installing approximately 50 linear feet of 12-inch diameter High-Density Polyethylene (HDPE) pressure sewer; installation of approximately 70 linear feet of 12-inch diameter Polyvinyl Chloride (PVC) gravity sewer and new sewer manhole; demolition of an existing sewage lift station including the wet well, valve vault, and associated electrical work; installation of a new a sewage pump station with submersible pumps, new wet well, valve vault, along with associated electrical work; and, installation of a new portable generator, pump controls, pump controls rack, along with associated electrical work; and site development including earthwork and paving with associated site utilities; and other miscellaneous items of work.