Downtown Street Improvements - Phase I

Bid Due Date: blank 11/22/2016

Pre-Bid Meeting:

Type of Solicitation: Bid
Bid/RFP Number: BE17-137
Date Advertised: 
Construction Estimate: $1,217,000
Plan Holders List: Current List
Cost of Bid Documents: $35
Project Description:

This Project consists of reconstruction of South Franklin Street from Front Street to Admiral Way.

Result

Low Bidder: Arete Construction

Bid Opening/Proposal Date: 11/22/2016
Bid Amount: $1,155,855
Bid/RFP Result Summary: View Document
Award Date: 0000-00-00
Award Amount: $1,155,855