CDD Logo

Egan Water System Replacement

Bid Due Date: blank 7/13/2016

Pre-Bid Meeting:

Type of Solicitation: Bid
Bid/RFP Number: E17-022
Date Advertised: 
Construction Estimate: $578,000
Plan Holders List: Current List
Cost of Bid Documents: $35
Project Description:

This Project consists of replacement of the ductile iron water main and associated services with HDPE along Egan Drive from West Ninth to Glacier Avenue and from Willoughby Avenue to Main Street, and miscellaneous items of work.

Result

Low Bidder: Southeast Earthmovers

Bid Opening/Proposal Date: 7/13/2016
Bid Amount: $554,961.00
Bid/RFP Result Summary: View Document
Award Date: 0000-00-00
Award Amount: 
Notice of Award: