Eaglecrest Underground Storage Tank Removal
Proposal Due Date: 6/3/2016
Type of Solicitation: RFQ
Bid/RFP Number: E16-257
Date Advertised:
Construction Estimate: Under $50,000
Plan Holders List: Current List
Cost of Bid Documents: -----
Removal of 8,000 gallon underground diesel fuel storage tank at the base of the bottom Ptarmigan Chair Lift.
Result
Low Bidder: G.R. Cheeseman Construction
Bid/RFP Documents:
RFQ E16-257
Addenda and Additional Information: