Statter Harbor Moorage Improvements
Bid Due Date: 4/17/2012
Pre-Bid Meeting:
Type of Solicitation: Bid
Bid/RFP Number: DH11-177
Date Advertised:
Construction Estimate: Approximately $9 Million
Plan Holders List: Current List
Cost of Bid Documents: $100
The Docks and Harbors Department of the City and Borough of Juneau is soliciting bids from qualified contractors to construct the Statter Harbor Moorage Improvements project.
Result
Low Bidder: Pacific Pile and Marine, LP
Bid Opening/Proposal Date: 4/17/2012
Bid Amount: $8,258,600
Bid/RFP Result Summary: View Document
Award Date: 0000-00-00
Award Amount:
Notice of Award:
Bid/RFP Documents:
Bid Document Download Instructions
Addenda and Additional Information:
Pre-bid Meeting Sign-in Sheet
Addendum No. 1
Addendum No. 2
Addendum No. 3
Addendum No. 4