Casey Shattuck Reconstruction, Phase V

Proposal Due Date: white pixel, space holder 3/11/2010

Pre-Bid Meeting Date: 

Type of Solicitation: Bid
Bid/RFP Number: E10-187


Description:

This Project consists of installation of an underground storm drainage system, replacement of water system and some segments of the sanitary sewer systems, replacement of the roadway embankment to a 24-inch depth, new asphalt pavement, concrete sidewalks and curb and gutter, removal and replacement of fences, relocation of landscaping items, removal of trees and shrubs, and miscellaneous related work.

Result

Low Bidder: Arete Contruction Corp.

Bid Opening/Proposal Date: 3/11/2010
Bid Amount: $1,221,904.00
Bid/RFP Result Summary: View Document
Award Date 0000-00-00
Award Amount: 
Notice of Award: View Document