Douglas 4th Street Utilities and Drainage

Proposal Due Date: 2021-04-13 white pixel, space holder

2021-03-31

Type of Solicitation: 
Bid
Bid/RFP Number: 
BE21-215
Date Advertised: 2021-03-18
Construction Estimate: $1,739,000.00
Plan Holders List: Current List
Cost of Bid Documents: -----

Description:

The WORK generally consists of: Replacement of multiple underground water transmission and distribution pipe networks (three different pressure zones) with new 10” and 14” HDPE pipe, water services, hydrants. WORK will include installation of temporary water systems to maintain service to the high pressure transmission network between PRVs, and temporary water systems to maintain service to affected residents; Replacement of the  existing the sewer systems with new manholes, 8” PVC sewer pipe, and 6” services with cleanouts; Replacement of the existing Bear Creek CMP culvert(s) and concrete headwalls with a new 84” diameter x 130’ long SRPE pipe culvert and new concrete headwalls, armor rock, and chainlink fencing; New underground storm drain system consisting of 12” and 18” CPP, area drains, and manhole with oil/water separator; Excavation, grading and shaping of the existing unpaved roads’ surface, and resurfacing with RAP material; and miscellaneous other improvements necessary for a complete project

Result

Low Bidder: Glacier State Contractors, Inc

Bid Opening/Proposal Date: 2021-04-13
Bid Amount: $1,639,211.00
Bid/RFP Result Summary: View Document
Award Date 
Award Amount: 
Notice of Award: View Document
Bid/RFP Documents: https://juneau.org/index.php?gf-download=2021%2F03%2FVOLUME-II_-BE21-215_Drawings.pdf&form-id=96&field-id=72&hash=6a01614c9b208c5a554f97010cb96edfee9a6e4359a09e77b102fe10795fd8eb
https://juneau.org/index.php?gf-download=2021%2F03%2FVOLUME-1-BE21-215.pdf&form-id=96&field-id=72&hash=fbc2b2e05c0ed73a4fdd1fa6b86a6f96379164f0443a7575731f67405b2f362d