Seawalk - Bridge to Gold Creek, Phase III
Proposal Due Date:
10/20/2016
Type of Solicitation:
Bid
Bid/RFP Number: E16-128
Date Advertised: 9/9/2016
Construction Estimate: $3.3 Million
Plan Holders List: Current List
Cost of Bid Documents: $100
Description:
This work consists of final completion of the bridge to Gold Creek segment of the Downtown Seawalk, including Bridge Park at the northern terminus of the Seawalk.
Result
Low Bidder: Admiralty Construction, Inc.
Bid Opening/Proposal Date: 10/20/2016
Bid Amount: $2,961,791.00
Bid/RFP Result Summary: View Document